March 2016
March 2017
Scope of the Eti Soda 154kV Extension Project:
1- Construction Projects:
Reinforced concrete projects
Architectural Project
Mechanical Installation Project
Electrical Installation Projects
Lighting Installation Project
Force Installation Project
Lightning Rod Installation Plan
Electrical outlet Installation Project
Telephone-Data plan
Basic grounding plan
Fire detection plan
Construction Projects of Transformer (62.5MVA,25MVA and 2x1600kVA)
2- Primer&Seconder Projects:
Single Line Diagrams (HV/MV/LV)
Switchyard Primer Projects:
General Layout Plan
General Location Plan
Switchyard Cross Sections
Construction Based – Channel
Grounding
Lighting
154kV Beypazarı Line Feeder Seconder Project
154kV Transformer-E Feeder Seconder Project
Transformer Seconder Projects (62.5MVA,25MVA)
Tr-E Feeder Electrical Diagrams (Relay Panel)
Tr-E Electric Meter Panel Project
Tr-E Seconder - Protection Relay Panel Project
DCS – RTU Panel Project
MV Switchgear Projects
MV Electrical Schematic Drawings (6.3kV&11kV)
MV Companzation Projects
LV Panel – AC&DC panel&Companzation(2x500kVAR) Projects
154kV Tr-E Feeder Cable List
154kV Beypazarı Line Feeder Cable List
MV&LV Power Cable Lists
MV&LV Control System Cable List
3- Construction of Metal Clad(MC) - MV Building
4- Construction foundation of the 62.5MVA (154/11kV) Main Transformer
5- Construction foundation of the 25MVA (11/6.3kV) Power Transformer
6- Construction foundation of the 2x1600KVA(6.3/0.4kV) Auxiliary(Service) Transformers
7- Steel construction foundations of pylons and 154kV primer equipments
8- Installation of Energy Transmission Line Equipments (Galvanized HV poles, 795 MCM)
assembly and disassembly of Galvanized HV poles
assembly and disassembly of 795 MCM conductor
9- Protection and Control Systems
10- Installation of 62.5MVA, 25MVA and 2x1600KVA Transformers
11- Installation of MV switchgears & MV Compensations & Cable Trays & MV power and control cables
12- Installation of DCS Equipments:
400V AC distribution panels,
LV Companzation panels (2x 500kVAR),
110V DC panel,
110 DC Redresors,
UPSs,
Battery groups,
Main Transformer Protection Relay Panels,
Rack Cabinet (Servers, Fiberoptic Communication),
RTU,
Counter Panel,
LV power and control cables,
Security - CCTV,
Fire Protection Systems (for Main Transformer&MV building)
13- Installation of 154kV Switchyard Equipments:
Steel constructions,
Circuit Breakers,
Disconnectors,
CTs&VTs,
Connection terminals,
SDK panel,
Substation Control building panels,
earthing conductor,
external lightings,
Security – CCTV
14- Testing and Activating (2T plant, 2T switchyard,MV Switchgears, SCADA-ABB microSCADA sys600)
154kV Tr-E&Beypazarı Feeder Primer Tests:
AC&DC Insulation Test(%PF) of CTs&VTs&Paradufr,
Secondary Voltages of VTs,
Contact Transition Resistances of busbar disconnectors, line disconnectors, line earthing switchs and Circuit Brakers(GE&Alstom),
On / off time of CBs
154kV Tr-E&Beypazarı Feeder Seconder Tests:
Load-Burden Test of VTs
Ratio, Polarity and Load Test for CTs
Saturation and Winding Resistance Test of CTs
154kV Tr-E Relay Tests:
ABB REF615 Relay Test - Overcurrent Protection Test
ABB RED670 – Distance Protection Test
ABB RED670 – Line Differantial Protection Test
ABB RED670 – Distance Calculation Test
154kV Tr-E Main&Spare Counter Index Tests
MV Switchgear Tests:
AC Insulation(%PF) Test of CBs
On / off time of CBs
Contact Transition Resistances of CBs
Polarity Test(AC Insulation-%PF) of CTs,VTs and Surge Arresters
Main busbar HV and Contact Resistance Tests
Ratio and Load Test for CTs
Saturation and Winding Resistance Test of CTs
Relay Tests (Overcurrent Protection, Earthing fault, Differantial Protection (Trip time, Harmonic Restraint)
15- Education of Primer and Seconder (Relay(GE&ABB), RTU, SCADA)
Subcontractors:
KAYAP İnşaat
Aktifsel Enerji
Alayapım Mühendislik
Kontrolmatik
GES Genel Elektrik Sistemleri Yapım ve Mühendislik A.Ş.
Atılan Mühendislik
SAN-EL Mühendislik
Power Elektronik
EAE Elektrik A.Ş.
Girişim Elektrik
Radsan
Erke Elektrik